PV and EV to ClipboardStatusin v0.8 DescriptionCalculates daily planned and earned value. How to UseThe script calculates the earned value and planned value for each day of the project. The data is placed into the clipboard in a format ready for a spreadsheet program. The format is: How It WorksTasks are scanned and effort is totalled by day. The first and last project dates are identified. A line is written to the clipboard for every day in that range. CritiqueThis is an experiment in how to best handle earned value calculations. The Update Measurements script is another. ContributorsBrian |
Download GanttPV:InstructionsWindows (v0.11b) Windows 98 (v0.7) MacOS 10.4 or later (v0.11b) MacOS 10.2 or 10.3 (v0.7) Source [Linux, Unix] (v0.11b) Release Notes (v0.11) Other LinksAlexander's FAQPureViolet.net Simple Project Management Using GanttPV (must read!) Recommended Books![]() Simple Project Management: The Book Managing Projects with GanttPV |